Building Project Updates

Building Construction Update December 8, 2016

Roberson Contracting is continuing the brick installation on the exterior of the church and they are progressing well. Capital Contractors will be framing the Cupula area and should have this area completed by Christmas. All exterior windows have been installed. Our church is beginning to develop its own character and I hope you have been impressed by its overall beauty.  

Building Construction Update October 27, 2016

Truss framing will start over the Narthex area on 11/1/16 and continue throughout the week. Capital Interiors is 85% complete with exterior sheathing and will start mulling window framing on 10/31/16. Roberson Contracting is starting brick installation on 10/31/16. We are hopeful the complete church will be under roof in 3 weeks. Over the next month the majority of work will involve the placement of windows, roof and bricks. We are still on schedule for our dedication with the Bishop on 3/21/16. Thanks to all for your continued support of this project.