Pastoral Center
The Pastoral Center Campaign

The “Pastoral Center” Update April 2025
The Pastoral Center will be a 10,500-foot structure that will house classrooms for religious education, meeting rooms for ministries within our parish and provide offices for all parish staff. We are anxious to begin this new journey in our parish development because this will provide the needed space to expand our religious education endeavors, offer additional programs to spiritually feed our parishioners and provide an improved productive work environment for our staff.
On April 2, 2025, James City Country approved our site plan to build the Pastoral Center and a special thanks goes out to Mark Rinaldi who spearheaded this effort for St. Olaf. The Building Committee met to discuss the “General Contractor’s Qualifications and Fee for Construction” proposals from four construction companies. The Building Committee selected two contracting firms: W. M. Jordan Company and Henderson Inc. On May 2, 2025, a subcommittee will meet in the offices of Guernsey Tingle to interview representatives from these construction companies and will make a final decision on who will build the Pastoral Center. Representatives from St. Olaf will meet with the Building and Renovation Committee (BARC) from the Diocese of Richmond in July for final approval of this project. Once we receive permission from the Diocese of Richmond, we will schedule our groundbreaking ceremony. Exciting times ahead!
Please pray for the continued success of this project.
The “Pastoral Center” Update March 2025
The Pastoral Center will be a 10,500-foot structure that will house classrooms for religious education, meeting rooms for all ministries within our parish and provide offices for all parish staff. We are anxious to begin this new journey in our parish because this will provide the needed space to expand our religious education efforts, offer more programs to spiritually feed our parishioners and provide a more productive work environment for our staff. At this time, we are preparing for a ground breaking ceremony in the Summer/Fall timeframe. There are several tasks that need to be accomplished before we can begin to build. We are awaiting approval of our Site Plan from James City County and anticipate approval in the next few weeks. The Building Committee is working closely with our architectural firm Guernsey Tingle to enhance the interior design of our building. The Building Committee meets monthly to discuss improvements/changes in the interior and exterior design. We will also have to appear before the Building and Renovation Committee for final approval of this project from the Dioceses of Richmond. This has been a sustained effort over many months by many individuals from our parish and we want to thank them for their dedication and desire to make this an extraordinary addition to our campus. More news to come in the approaching weeks. Please pray for the success of this project.
Capital Campaign Update
Exciting News about the Pastoral Center
12/20/2024
- The over-all results from the Capital Campaign were 354 Gifts over $2.5 Million.
- On November 27, 2024 AES Consulting Engineers presented our Site Plan to James City County for approval.
- The St. Olaf Building Committee in concert with Guernsey Tingle Architects meet monthly to discuss changes and improvements to the interior design of the building.
- Anticipated “Ground Breaking” for the Pastoral Center is the summer of 2025.

Pastoral Center Update - September 2024
The Capital Campaign was a success, raising slightly more than our goal of $2.5 million in pledges. We will be able to move forward with building when we have $1.25 million collected. As of this date, we have in hand about $500,000. In the meantime, the Construction Committee is finalizing the design for the building, and once completed can proceed with the production of the construction drawings. The drawings will need approvals of the county and diocese, then once completed the job will be out for contractors to bid. Barring unforeseen complications, optimistically, we may be able to break ground late Spring of 2025. We may be complete early in 2026.
Please keep the project in prayer, that all goes well.